2012年pmp考試模擬試題及答案(二)
QUEST Project management provides organizations with a methodology to: 
A Become more efficient and effective in accomplishing goals that cannot be handled well by 
the traditional structure 
B Manage high risk repetitive work 
C Provide clients with multiple points of contact 
D Provide guidance in accomplishing repetitive activities 
E All of the above 
A 
QUEST Configuration (baseline) control monitors performance against the 
A scope baseline 
B original schedule 
C original budget 
D All of the above. 
E None of the above. 
A 
QUEST A summary WBS is usually developed in the 
A Conceptual phase 
B implementation phase 
C planning phase 
D close-out phase 
E All of the above phases 
A 
QUEST A project may be defined as _____ 
A an integrated approach to managing projects 
B a coordinated undertaking of interrelated activities. 
C a group of activities directed by a project manger over a life cycle 
D an undertaking with a defined starting point and defined objectives 
E All of the above. 
D 
QUEST Approval to proceed is normally made at the end of the _____ phase of a typical project. 
A conceptual 
B development 
C implementation 
D execution 
E close-out 
A 
QUEST Lessons learned are most often based upon project historical records. Lessons learned can 
be used to: 
A See what mistakes others have made 
B See how others have solved problems 
C Predict trends, highlight problems and identify alternatives 
D All of the above 
E A and B only 
D 
QUEST A program can best be described as: 
A A grouping of related activities which last two years or more 
B The first major subdivision of a project 
C A grouping of projects, similar in nature, which support a product or product line and 
have no definable end point 
D A product line 
E Another name for a project 
C 
QUEST Ensuring that all work is both authorized and funded by contractual documentation is the 
responsibility of: 
A The project manager 
B The functional manager 
C The project sponsor 
D The client 
E All of the above 
A 
QUEST The project charter is a document designed to tell _____ exactly what the project 
entails. 
A The project manager 
B The project office 
C The project team 
D The project sponsor 
E Anyone associated with the project 
E 
QUEST Work authorization forms are needed in order to: 
A Authorize line organizations to charge against the project 
B Establish an audit trail 
C Develop a structured methodology for release of funds 
D All of the above 
E A and C only 
D 
QUEST The scope baseline/project charter is prepared by the: 
A Project manager 
B Project manager and project office 
C Project manager, project office and functional team 
D Project manager, project office, functional team and project sponsor 
E Project manager, project sponsor and customer/user 
E 
QUEST Typical characteristics of a work package include: 
A Representation of units of work at a level where work is performed 
B Clearly distinguishes one work package from all others assigned to a single functional 
group 
C Limits the work to be performed to relatively short periods of time 
D All of the above 
E A and B only 
E 
QUEST Problems can occur in properly defining a project because: 
A Project goals may not be agreeable to all parties 
B The plan was "too loose," thus allowing priorities to change 
C Low turnover of project personnel 
D Too much communication between the client and project personnel 
E The project objectives were quantified 
A 
QUEST In preparing a good project definition, experienced project managers will: 
A Concentrate mainly on the end product rather than costs or benefits. These come later. 
B Realize that only the "tip of the iceberg" may be showing. As a project manager, you must 
get beneath it. 
C Understand that a project definition/plan is a dynamic rather than static tool, and thus 
subject to change. 
D Try to convert objectives into quantifiable terms. 
E All of the above 
E 
QUEST Project life cycles provide a better means of measurement of progress and control. The 
four phases of a project are conceptual development, _____, _____, and _____. 
A Preliminary planning, detail planning, closeout 
B Implementation, reporting, termination 
C Development, implementation, termination 
D Execution, reporting, finishing 
E Implementation, termination, post-audit review 
C 
QUEST The contractual statement of work (CSOW) 
A Must be the same as the proposal statement of work 
B Does not identify reporting requirements 
C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work 
D Identifies the contractor’s organizational structure for the project 
E All of the above 
C 
QUEST Which of the following can result in misinterpretation of the statement of work? 
A Using imprecise language (i.e. nearly, approximately) 
B Mixing tasks, specifications, special instructions and approvals 
C No pattern, structure or chronological order 
D Wide variation in the size of tasks or details of work 
E All of the above 
E 
QUEST A project manager believes that modifying the scope of the project may provide added value 
for the customer. The project manager should: 
A Change the scope baseline 
B Prepare a variance report 
C Call a meeting of the configuration control board 
D Change the project’s objectives 
E Postpone the modification until a separate enhancement project is funded after this 
project is completed according to the original baseline 
E 
QUEST The document authorizing functional areas to charge against the project is the: 
A Work authorization form 
B Scope baseline 
C Project charter 
D Management plan 
E Linear responsibility chart 
A 