2012年pmp考試模擬試題及答案(五)
QUEST A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be: 
A 4 weeks 
B 5 weeks 
C 6 weeks 
D 7 weeks 
E None of the above. 
B 
QUEST Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to: 
A All activities. 
B Only those activities with the longest time durations. 
C Those activities on the critical path begining with the longest time duration activities. 
D Those activities with the greatest degree of risk. 
E None of the above. 
C 
QUEST A network has been developed with resources from six different departments. One of the six departments has just informed you that they can increase the number of employees from 5 to 8. This will result in: 
A A shortening of the critical path. 
B A shortening of the noncritical path. 
C A decrease in the total cost of the project. 
D An increase in the cost of the project. 
E A through D are possible based upon where the resources are deployed. 
E 
QUEST Bar charts are most appropriate for: 
A Comparing actual to planned performance to each activity. 
B Showing slack time. 
C Showing critical path dependencies. 
D Showing which activities can be rearranged in parallel. 
E All of the above. 
A 
QUEST A non-critical path activity is completed in half the time. Then, 
A The critical path is also reduced. 
B The slack in the path containing this activity will increase. 
C The total cost for this activity has decreased. 
D Manpower from this activity can be assigned to other activities. 
E All of the above. 
B 
QUEST Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the _____ and identification of the _____ . 
A Slack for each activity, critical path. 
B Slack for each activity, high risk activities. 
C Manpower shortages, high risk activities. 
D High risk activities, non-critical paths. 
E Manpower availability, contingency plans. 
A 
QUEST ADM is an activity-on-arrow method. In this method, a dummy activity: 
A Denotes a critical path relationship. 
B Denotes any dependency relationship. 
C Shows slack. 
D Identifies customer deliverables dates. 
E Identifies customer team meeting dates. 
B 
QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ . 
A Project specification tree. 
B Customer's deliverable list. 
C Customer's milestone dates. 
D Work breakdown structure. 
E Listing of customer team meeting dates. 
D 
QUEST The critical path in a network is the path that: 
A Has the greatest degree of risk. 
B Will elongate the project if the activities on this path take longer than anticipated. 
C Must be completed before all other paths. 
D All of the above. 
E A and B only. 
B 
QUEST The major difference between PERT and CPM networks is: 
A PERT requires three time estimates whereas CPM requires one time estimate. 
B PERT is used for construction projects whereas CPM is used for R & D. 
C PERT addresses only time whereas CPM also includes cost and resource availability. 
D PERT requires computer solutions whereas CPM is a manual technique. 
E PERT is measured in days whereas CPM uses weeks or months. 
A 
QUEST A calendar that identifies when a project may be performed on an activity is called a: 
A Project calendar. 
B Resource calendar. 
C Milestone point. 
D Key point. 
E Work unit. 
A 
QUEST Planning activities such that predetermined resource availability pools are not exceeded is called: 
A Resource leveling. 
B Manpower leveling. 
C Resource limited planning. 
D Manpower planning. 
E Manpower contingency planning. 
C 
QUEST A comparison of completion status to baseline is referred to as _____. 
A Earned value measurement. 
B Percent complete. 
C ACWP. 
D BCWS 
E None of above. 
A 
QUEST The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as: 
A Slack 
B Free float. 
C Restricted float. 
D Level float. 
E Lag 
E 
QUEST Overlapping activities on a project, such as design and construction, is referred to as: 
A Fast tracking 
B Risk conversion. 
C Parallel management. 
D Process improvement. 
E Synchronous manufacturing 
A 
QUEST A computer tape which contains historical project information is called ____ tape. 
A Database 
B Baseline. 
C Archive. 
D Lessons learned. 
E Life cycle summary. 
C 
QUEST Which method shown below is acceptable for reducing cost or shortening the schedule? 
A "Crashing" 
B Changing scope. 
C Performing activities in parallel rather than in series. 
D All of the above. 
E A and C only. 
D 
QUEST In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs. 
A Increase, decrease. 
B Increase, increase 
C Increase, increase or decrease. 
D Decrease, decrease. 
E Decrease, increase. 
B 
QUEST Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____. 
A Allocation. 
B Partitioning 
C Leveling 
D Quantification. 
E None of above. 
A 