2010年P(guān)MP美國項目管理考試習(xí)題及答案五十五
QUEST A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A Parametric
B Definitive.
C Budget
D Bottom up.
E Top down.
參考答案:C
QUEST The most precise or accurate estimate for determining project costs is the _____ estimate.
A Definitive.
B Analogy
C Budget
D Modified standards.
E Rule of thumb.
參考答案:A
QUEST Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.
A Definitive, bottom up.
B Analogy, top down.
C Parametric, bottom up.
D Parametric, top down.
E Analogy, bottom up.
參考答案:D
QUEST A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
A Inventory control.
B Materials management.
C Procurement.
D All of the above.
E A and C only.
參考答案:B

QUEST There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
A Management reserve, unplanned allowance fund.
B Management reserve, contingency.
C Contingency fund, management reserve.
D Unplanned allowance fund, budgetary reserve.
E Unplanned reserve, planned reserve.
參考答案:C