QUEST Which phase of the project life cycle typically has the highest uncertainty and risk associated with it? 
A concept 
B development 
C execution 
D conclusion 
E All of the above. 
參考答案:A
QUEST By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following: 
A Significantly reduce project risks 
B eliminate project risks 
C provide a rational basis for better decision making 
D identify risks, their impact(s), and any appropriate responses 
E None of the above. 
參考答案:B
QUEST A contractor estimates that a project has a 0.5 probability of $200,000 profit and 0.3 probability of $50,000 loss.  The expected monetary value of this project is: 
A ¥200,000 
B ¥150,000 
C ¥85,000 
D ¥50,000 
E None of the above. 
參考答案:C
QUEST Which of the following diagrams is most useful in impact analysis: 
A arrow diagrams 
B precedence diagrams 
C decision trees 
D Pareto diagrams 
E cause and effects diagrams 
參考答案:C

QUEST Which of the following risks are generally considered unpredictable: 
A business risk 
B financial risk 
C inflation 
D natural hazards 
E taxes 
參考答案:C